Where is Site To North East Of, Lochcraigs Farm up to?
Each status below comes from a named source and date.
Solar PV · Scotland
Planning
- Planning
- Granted
- 13 Aug 2015
- DESNZ REPD, 3 Aug 2026
- Construction
- Built
- 15 Oct 2016
- DESNZ REPD, 3 Aug 2026
- Operational status
- Operational
- 31 Mar 2017
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Solar PV project, epj_60d04150c3afbe70
Measures
- Rated power
- 5.0 MW
- Connection capacity
- Not published
- Storage energy
- Not published