Projects
Where is Kingdom of Fife Community Wind Park up to?
Each status below comes from a named source and date.
Onshore wind · Scotland
Planning
- Planning
- Refused
- 1 Oct 2013
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Onshore wind project, epj_6134ffc723f6d6e6
Measures
- Rated power
- 12.0 MW
- Connection capacity
- Not published
- Storage energy
- Not published