Projects
Where is Breezy Hill, North Kyle Forest Estate - BESS up to?
Each status below comes from a named source and date.
Battery · Scotland
Planning
- Planning
- Application submitted
- 8 May 2025
- DESNZ REPD, 3 Aug 2026
- Operational status
- Proposed
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Battery project, epj_61f2449bfb0ae75e
Measures
- Rated power
- 40.0 MW
- Connection capacity
- Not published
- Storage energy
- Not published