Projects
Where is Meadow Stores, Ormiston - Solar Panels up to?
Each status below comes from a named source and date.
Solar PV · Scotland
Planning
- Planning
- Granted
- 1 Nov 2024
- DESNZ REPD, 3 Aug 2026
- Construction
- Not started
- DESNZ REPD, 3 Aug 2026
- Operational status
- Proposed
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Solar PV project, epj_6238bbc52819ee5b
Measures
- Rated power
- 0.2 MW
- Connection capacity
- Not published
- Storage energy
- Not published