Solar PV · England, Yorkshire and Humber
Planning
- Planning
- Granted
- 21 Apr 2023
- DESNZ REPD, 3 Aug 2026
- Construction
- Not started
- DESNZ REPD, 3 Aug 2026
- Operational status
- Proposed
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Solar PV project, epj_6274c81b3565e9ae
Measures
- Rated power
- 49.9 MW
- Connection capacity
- Not published
- Storage energy
- Not published