Projects
Where is Greenbank Caravan & Trailers, Hillhead Of Phingask - Battery Storage up to?
Each status below comes from a named source and date.
Battery · Scotland
Planning
- Planning
- Granted
- 30 Jan 2023
- DESNZ REPD, 3 Aug 2026
- Construction
- Not started
- DESNZ REPD, 3 Aug 2026
- Operational status
- Proposed
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Battery project, epj_64cfe4e3bb904da7
Measures
- Rated power
- 50.0 MW
- Connection capacity
- Not published
- Storage energy
- Not published