Where is Red Barn - Solar Farm & Battery Storage up to?
Each status below comes from a named source and date.
Battery · England, South West
Planning
- Planning
- Granted
- 27 Jan 2025
- DESNZ REPD, 3 Aug 2026
- Construction
- Not started
- DESNZ REPD, 3 Aug 2026
- Operational status
- Proposed
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Battery project, epj_64f6cdb90ea7b371
Measures
- Rated power
- 40.0 MW
- Connection capacity
- Not published
- Storage energy
- Not published