Biomass · Scotland
Planning
- Planning
- Granted
- 2 Feb 2015
- DESNZ REPD, 3 Aug 2026
- Construction
- Built
- 15 Jan 2017
- DESNZ REPD, 3 Aug 2026
- Operational status
- Operational
- 15 Jul 2017
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Biomass project, epj_65d12370e4ae3afe
Measures
- Rated power
- 5.6 MW
- Connection capacity
- Not published
- Storage energy
- Not published