Where is Acharn Forest Killin Biomass Plant up to?

Each status below comes from a named source and date.

Biomass · Scotland

Planning

Planning
Granted
2 Feb 2015
DESNZ REPD, 3 Aug 2026
Construction
Built
15 Jan 2017
DESNZ REPD, 3 Aug 2026
Operational status
Operational
15 Jul 2017
DESNZ REPD, 3 Aug 2026

Connection

Connection
Biomass project, epj_65d12370e4ae3afe

Measures

Rated power
5.6 MW
Connection capacity
Not published
Storage energy
Not published