Solar PV · England, North West
Planning
- Planning
- Granted
- 25 Mar 2024
- DESNZ REPD, 3 Aug 2026
- Construction
- Not started
- DESNZ REPD, 3 Aug 2026
- Operational status
- Proposed
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Solar PV project, epj_66419d5b9ae0bee4
Measures
- Rated power
- 0.4 MW
- Connection capacity
- Not published
- Storage energy
- Not published