Battery · Scotland
Planning
- Planning
- Granted
- 29 Mar 2023
- DESNZ REPD, 3 Aug 2026
- Construction
- Not started
- DESNZ REPD, 3 Aug 2026
- Operational status
- Proposed
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Battery project, epj_66f36fd37decbeda
Measures
- Rated power
- 15.0 MW
- Connection capacity
- Not published
- Storage energy
- Not published