Battery · England, Yorkshire and Humber
Planning
- Planning
- Granted
- 24 Apr 2026
- DESNZ REPD, 3 Aug 2026
- Construction
- Not started
- DESNZ REPD, 3 Aug 2026
- Operational status
- Proposed
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Battery project, epj_66ff92c3b623789e
Measures
- Rated power
- 375.0 MW
- Connection capacity
- Not published
- Storage energy
- Not published