Biomass · England, South East
Planning
- Planning
- Granted
- 29 May 2012
- DESNZ REPD, 3 Aug 2026
- Construction
- Built
- DESNZ REPD, 3 Aug 2026
- Operational status
- Operational
- 15 Dec 2012
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Biomass project, epj_6722a0fcd2d52868
Measures
- Rated power
- 1.5 MW
- Connection capacity
- Not published
- Storage energy
- Not published