Hydrogen · Wales
Planning
- Planning
- Granted
- 13 Feb 2026
- DESNZ REPD, 3 Aug 2026
- Construction
- Not started
- DESNZ REPD, 3 Aug 2026
- Operational status
- Proposed
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Hydrogen project, epj_67866d3ea26e915f
Measures
- Rated power
- 8.0 MW
- Connection capacity
- Not published
- Storage energy
- Not published