Projects
Where is Boxgrove Common, Tinwood Lane - Battery Energy Storage System up to?
Each status below comes from a named source and date.
Battery · England, South East
Planning
- Planning
- Granted
- 23 Jul 2025
- DESNZ REPD, 3 Aug 2026
- Construction
- Not started
- DESNZ REPD, 3 Aug 2026
- Operational status
- Proposed
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Battery project, epj_68433c9fa182aefd
Measures
- Rated power
- 70.0 MW
- Connection capacity
- Not published
- Storage energy
- Not published