Projects
Where is Walshaw House, Regent Street - Battery Energy Storage up to?
Each status below comes from a named source and date.
Battery · England, North West
Planning
- Planning
- Granted
- 14 Dec 2023
- DESNZ REPD, 3 Aug 2026
- Construction
- Not started
- DESNZ REPD, 3 Aug 2026
- Operational status
- Proposed
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Battery project, epj_6c145efd7d89014f
Measures
- Rated power
- 100.0 MW
- Connection capacity
- Not published
- Storage energy
- Not published