Battery · England, North East
Planning
- Planning
- Granted
- 16 Jun 2021
- DESNZ REPD, 3 Aug 2026
- Construction
- Under construction
- 1 Oct 2022
- DESNZ REPD, 3 Aug 2026
- Operational status
- Proposed
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Battery project, epj_6cbd18584e2c75be
Measures
- Rated power
- 20.0 MW
- Connection capacity
- Not published
- Storage energy
- Not published