Battery · England, South East
Planning
- Planning
- Granted
- 1 Nov 2022
- DESNZ REPD, 3 Aug 2026
- Construction
- Under construction
- 28 Aug 2023
- DESNZ REPD, 3 Aug 2026
- Operational status
- Proposed
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Battery project, epj_701d40ce3276b581
Measures
- Rated power
- 2.0 MW
- Connection capacity
- Not published
- Storage energy
- Not published