Where is Burbo Bank Extension (Burbo Bank 2) up to?

Each status below comes from a named source and date.

Offshore wind · England, Offshore

Planning

Planning
Granted
10 Dec 2014
DESNZ REPD, 3 Aug 2026
Construction
Built
10 Jun 2016
DESNZ REPD, 3 Aug 2026
Operational status
Operational
27 Apr 2017
DESNZ REPD, 3 Aug 2026

Connection

Connection
Offshore wind project, epj_71b4fe6c29710328

Measures

Rated power
258.0 MW
Connection capacity
Not published
Storage energy
Not published