Projects
Where is Glenniston Farm, Auchtertool - Solar Farm up to?
Each status below comes from a named source and date.
Solar PV · Scotland
Planning
- Planning
- Granted
- 5 Apr 2024
- DESNZ REPD, 3 Aug 2026
- Construction
- Not started
- DESNZ REPD, 3 Aug 2026
- Operational status
- Proposed
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Solar PV project, epj_72760beaa25dc327
Measures
- Rated power
- 39.0 MW
- Connection capacity
- Not published
- Storage energy
- Not published