Projects
Where is Lincoln Farm up to?
Each status below comes from a named source and date.
Solar PV · England, East Midlands
Planning
- Planning
- Granted
- 20 Oct 2014
- DESNZ REPD, 3 Aug 2026
- Construction
- Built
- 1 May 2016
- DESNZ REPD, 3 Aug 2026
- Operational status
- Operational
- 25 Mar 2016
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Solar PV project, epj_72943fb725c0533c
Measures
- Rated power
- 11.4 MW
- Connection capacity
- Not published
- Storage energy
- Not published