Projects
Where is Clayhill up to?
Each status below comes from a named source and date.
Battery · England, Eastern
Planning
- Planning
- Granted
- 28 Jan 2015
- DESNZ REPD, 3 Aug 2026
- Construction
- Built
- 24 Apr 2016
- DESNZ REPD, 3 Aug 2026
- Operational status
- Operational
- 24 Jun 2016
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Battery project, epj_73a9363b024874bb
Measures
- Rated power
- 6.0 MW
- Connection capacity
- Not published
- Storage energy
- Not published