Where is Bilbster Wind Farm up to?
Each status below comes from a named source and date.
Onshore wind · Scotland
Planning
- Planning
- Granted
- DESNZ REPD, 3 Aug 2026
- Construction
- Built
- DESNZ REPD, 3 Aug 2026
- Operational status
- Operational
- 1 Feb 2008
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Onshore wind project, epj_751efc598cc3053c
Measures
- Rated power
- 3.9 MW
- Connection capacity
- Not published
- Storage energy
- Not published