Where is Blue Bell Lodge, Rye Common Lane - Battery Storage up to?
Each status below comes from a named source and date.
Battery · England, South East
Planning
- Planning
- Granted
- 22 May 2023
- DESNZ REPD, 3 Aug 2026
- Construction
- Not started
- DESNZ REPD, 3 Aug 2026
- Operational status
- Proposed
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Battery project, epj_75ce7d97b905f89c
Measures
- Rated power
- 49.5 MW
- Connection capacity
- Not published
- Storage energy
- Not published