Solar PV · England, North West
Planning
- Planning
- Granted
- 16 Jul 2015
- DESNZ REPD, 3 Aug 2026
- Construction
- Built
- 15 Jan 2016
- DESNZ REPD, 3 Aug 2026
- Operational status
- Operational
- 28 Mar 2016
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Solar PV project, epj_7bb8e13030e067a1
Measures
- Rated power
- 4.2 MW
- Connection capacity
- Not published
- Storage energy
- Not published