Onshore wind · Scotland
Planning
- Planning
- Granted
- 25 Aug 2016
- DESNZ REPD, 3 Aug 2026
- Construction
- Not started
- DESNZ REPD, 3 Aug 2026
- Operational status
- Proposed
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Onshore wind project, epj_7cdaef441b7effa8
Measures
- Rated power
- 12.3 MW
- Connection capacity
- Not published
- Storage energy
- Not published