Anaerobic digestion · England, Eastern

Planning

Planning
Granted
26 Mar 2012
DESNZ REPD, 3 Aug 2026
Construction
Built
31 Mar 2014
DESNZ REPD, 3 Aug 2026
Operational status
Operational
4 Jul 2016
DESNZ REPD, 3 Aug 2026