Where is Ratty's Lane Sustainable Energy Facility (Waste AD) up to?
Each status below comes from a named source and date.
Anaerobic digestion · England, Eastern
Planning
- Planning
- Granted
- 26 Mar 2012
- DESNZ REPD, 3 Aug 2026
- Construction
- Built
- 31 Mar 2014
- DESNZ REPD, 3 Aug 2026
- Operational status
- Operational
- 4 Jul 2016
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Anaerobic digestion project, epj_7e8331ec33d23372
Measures
- Rated power
- 3.0 MW
- Connection capacity
- Not published
- Storage energy
- Not published