Solar PV · England, North West

Planning

Planning
Granted
17 Apr 2025
DESNZ REPD, 3 Aug 2026
Construction
Not started
DESNZ REPD, 3 Aug 2026
Operational status
Proposed
DESNZ REPD, 3 Aug 2026

Connection

Connection
Solar PV project, epj_8317ce2d35187ec4

Measures

Rated power
0.3 MW
Connection capacity
Not published
Storage energy
Not published