Where is Woodlands Farm Solar Park up to?

Each status below comes from a named source and date.

Solar PV · England, South East

Planning

Planning
Granted
7 May 2014
DESNZ REPD, 3 Aug 2026
Construction
Built
24 Nov 2014
DESNZ REPD, 3 Aug 2026
Operational status
Operational
30 Mar 2015
DESNZ REPD, 3 Aug 2026

Connection

Connection
Gate 1, Agreement held
31 Oct 2036
NESO TEC register, 13 Oct 2026

Measures

Rated power
10.0 MW
Connection capacity
227.5 MW
Storage energy
Not published