Projects
Where is Upper Farm solar park up to?
Each status below comes from a named source and date.
Solar PV · England, South East
Planning
- Planning
- Granted
- 12 Aug 2014
- DESNZ REPD, 3 Aug 2026
- Construction
- Built
- 15 Nov 2014
- DESNZ REPD, 3 Aug 2026
- Operational status
- Operational
- 30 Mar 2015
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Solar PV project, epj_8685c432919b5434
Measures
- Rated power
- 12.0 MW
- Connection capacity
- Not published
- Storage energy
- Not published