Projects
Where is Frodo Solar and Battery Energy Development up to?
Each status below comes from a named source and date.
Battery · Scotland
Planning
- Planning
- Granted
- 16 May 2023
- DESNZ REPD, 3 Aug 2026
- Construction
- Not started
- DESNZ REPD, 3 Aug 2026
- Operational status
- Proposed
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Battery project, epj_86f614287d031506
Measures
- Rated power
- 50.0 MW
- Connection capacity
- Not published
- Storage energy
- Not published