Projects
Where is Dura Park Bynea Industrial Site up to?
Each status below comes from a named source and date.
Solar PV · Wales
Planning
- Planning
- Granted
- 15 Dec 2015
- DESNZ REPD, 3 Aug 2026
- Construction
- Built
- 1 Sep 2015
- DESNZ REPD, 3 Aug 2026
- Operational status
- Operational
- 21 Dec 2015
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Solar PV project, epj_88af31cb7b489ce4
Measures
- Rated power
- 1.4 MW
- Connection capacity
- Not published
- Storage energy
- Not published