Projects
Where is Southern Counties Shooting Ground Phase 2 up to?
Each status below comes from a named source and date.
Solar PV · England, South West
Planning
- Planning
- Granted
- 8 Jan 2016
- DESNZ REPD, 3 Aug 2026
- Construction
- Built
- 20 Sep 2016
- DESNZ REPD, 3 Aug 2026
- Operational status
- Operational
- 2 Feb 2017
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Solar PV project, epj_88daaf8fbd957d2e
Measures
- Rated power
- 5.0 MW
- Connection capacity
- Not published
- Storage energy
- Not published