Where is Southern Counties Shooting Ground Phase 2 up to?

Each status below comes from a named source and date.

Solar PV · England, South West

Planning

Planning
Granted
8 Jan 2016
DESNZ REPD, 3 Aug 2026
Construction
Built
20 Sep 2016
DESNZ REPD, 3 Aug 2026
Operational status
Operational
2 Feb 2017
DESNZ REPD, 3 Aug 2026

Connection

Connection
Solar PV project, epj_88daaf8fbd957d2e

Measures

Rated power
5.0 MW
Connection capacity
Not published
Storage energy
Not published