Where is Gonerby Moor, Great Gonerby - Solar Farm up to?

Each status below comes from a named source and date.

Solar PV · England, East Midlands

Planning

Planning
Granted
3 Nov 2021
DESNZ REPD, 3 Aug 2026
Construction
Built
1 May 2025
DESNZ REPD, 3 Aug 2026
Operational status
Operational
26 Jun 2026
DESNZ REPD, 3 Aug 2026

Connection

Connection
Solar PV project, epj_8b381686016372e8

Measures

Rated power
60.0 MW
Connection capacity
Not published
Storage energy
Not published