Projects
Where is Bryn Blaen Wind Farm up to?
Each status below comes from a named source and date.
Onshore wind · Wales
Planning
- Planning
- Granted
- 23 Aug 2016
- DESNZ REPD, 3 Aug 2026
- Construction
- Built
- 15 Jun 2017
- DESNZ REPD, 3 Aug 2026
- Operational status
- Operational
- 1 Jan 2019
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Onshore wind project, epj_8cdebc3fa4b0c95f
Measures
- Rated power
- 13.8 MW
- Connection capacity
- Not published
- Storage energy
- Not published