Biomass · England, East Midlands

Planning

Planning
Granted
22 Oct 2014
DESNZ REPD, 3 Aug 2026
Construction
Built
15 Dec 2015
DESNZ REPD, 3 Aug 2026
Operational status
Operational
15 Apr 2018
DESNZ REPD, 3 Aug 2026

Connection

Connection
Biomass project, epj_8d15ac03eeecccaa

Measures

Rated power
12.0 MW
Connection capacity
Not published
Storage energy
Not published