Grid

Projects

Projects

Where is Guildford Spectrum Leisure Centre, Parkway - Solar Panels up to?

Each status below comes from a named source and date.

Solar PV · England, South East

Planning

Planning
Granted
3 Jun 2026
DESNZ REPD, 3 Aug 2026
Construction
Not started
DESNZ REPD, 3 Aug 2026
Operational status
Proposed
DESNZ REPD, 3 Aug 2026

Connection

Connection
Solar PV project, epj_8e3b7048bc9f2b97

Measures

Rated power
0.6 MW
Connection capacity
Not published
Storage energy
Not published