Where is Land between Orton Park Farm up to?
Each status below comes from a named source and date.
Solar PV · England, North West
Planning
- Planning
- Granted
- 23 Sep 2015
- DESNZ REPD, 3 Aug 2026
- Construction
- Built
- 22 Jan 2016
- DESNZ REPD, 3 Aug 2026
- Operational status
- Operational
- 29 Mar 2016
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Solar PV project, epj_9213c86dc4fb3dac
Measures
- Rated power
- 6.4 MW
- Connection capacity
- Not published
- Storage energy
- Not published