Where is Land between Orton Park Farm up to?

Each status below comes from a named source and date.

Solar PV · England, North West

Planning

Planning
Granted
23 Sep 2015
DESNZ REPD, 3 Aug 2026
Construction
Built
22 Jan 2016
DESNZ REPD, 3 Aug 2026
Operational status
Operational
29 Mar 2016
DESNZ REPD, 3 Aug 2026

Connection

Connection
Solar PV project, epj_9213c86dc4fb3dac

Measures

Rated power
6.4 MW
Connection capacity
Not published
Storage energy
Not published