Where is Primrose Hill Farm up to?

Each status below comes from a named source and date.

Solar PV · England, East Midlands

Planning

Planning
Granted
9 Aug 2014
DESNZ REPD, 3 Aug 2026
Construction
Built
15 Jan 2015
DESNZ REPD, 3 Aug 2026
Operational status
Operational
25 Mar 2015
DESNZ REPD, 3 Aug 2026

Connection

Connection
Solar PV project, epj_92969ff46423a5b2

Measures

Rated power
3.7 MW
Connection capacity
Not published
Storage energy
Not published