Where is Gleneagles Hotel Biomass Boiler Plant Room up to?

Each status below comes from a named source and date.

Biomass · Scotland

Planning

Planning
Granted
4 Feb 2021
DESNZ REPD, 3 Aug 2026
Construction
Built
DESNZ REPD, 3 Aug 2026
Operational status
Operational
1 Oct 2021
DESNZ REPD, 3 Aug 2026

Connection

Connection
Biomass project, epj_93c48198b6b0f4d2

Measures

Rated power
1.2 MW
Connection capacity
Not published
Storage energy
Not published