Grid

Projects

Projects

Where is Dormitories Star Inn Farm, Mains Of Fowlis - Battery Energy Storage up to?

Each status below comes from a named source and date.

Battery · Scotland

Planning

Planning
Granted
20 Dec 2023
DESNZ REPD, 3 Aug 2026
Construction
Not started
DESNZ REPD, 3 Aug 2026
Operational status
Proposed
DESNZ REPD, 3 Aug 2026

Connection

Connection
Battery project, epj_94fb4077ccb94990

Measures

Rated power
49.9 MW
Connection capacity
Not published
Storage energy
Not published