Solar PV · Scotland

Planning

Planning
Granted
18 Jan 2023
DESNZ REPD, 3 Aug 2026
Construction
Not started
DESNZ REPD, 3 Aug 2026
Operational status
Proposed
DESNZ REPD, 3 Aug 2026

Connection

Connection
Solar PV project, epj_959086f36fe59d1f

Measures

Rated power
2.0 MW
Connection capacity
Not published
Storage energy
Not published