Solar PV · England, Yorkshire and Humber
Planning
- Planning
- Application submitted
- 5 Jun 2025
- DESNZ REPD, 3 Aug 2026
- Operational status
- Proposed
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Solar PV project, epj_95a6a4aefca5fcdd
Measures
- Rated power
- 49.9 MW
- Connection capacity
- Not published
- Storage energy
- Not published