Projects
Where is Mynydd Bwllfa Wind Farm - Resubmission up to?
Each status below comes from a named source and date.
Onshore wind · Wales
Planning
- Planning
- Granted
- 1 Jun 2012
- DESNZ REPD, 3 Aug 2026
- Construction
- Built
- 1 Feb 2014
- DESNZ REPD, 3 Aug 2026
- Operational status
- Operational
- 8 May 2015
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Onshore wind project, epj_96c45100d3b45f10
Measures
- Rated power
- 22.5 MW
- Connection capacity
- Not published
- Storage energy
- Not published