Solar PV · England, South West
Planning
- Planning
- Granted
- 15 May 2013
- DESNZ REPD, 3 Aug 2026
- Construction
- Built
- 15 Nov 2013
- DESNZ REPD, 3 Aug 2026
- Operational status
- Operational
- 24 Mar 2014
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Solar PV project, epj_99b37c48d6b10af7
Measures
- Rated power
- 1.5 MW
- Connection capacity
- Not published
- Storage energy
- Not published