Where is Land at Morfa Camp up to?

Each status below comes from a named source and date.

Solar PV · Wales

Planning

Planning
Granted
19 Oct 2015
DESNZ REPD, 3 Aug 2026
Construction
Built
5 Jan 2016
DESNZ REPD, 3 Aug 2026
Operational status
Operational
20 Mar 2016
DESNZ REPD, 3 Aug 2026

Connection

Connection
Solar PV project, epj_9a20b41c40581c42

Measures

Rated power
2.8 MW
Connection capacity
Not published
Storage energy
Not published