Projects
Where is Fferm Bryn Bachau up to?
Each status below comes from a named source and date.
Solar PV · Wales
Planning
- Planning
- Granted
- 30 Sep 2015
- DESNZ REPD, 3 Aug 2026
- Construction
- Built
- 12 Jan 2016
- DESNZ REPD, 3 Aug 2026
- Operational status
- Operational
- 29 Mar 2016
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Solar PV project, epj_9a287848b4d1f46d
Measures
- Rated power
- 4.4 MW
- Connection capacity
- Not published
- Storage energy
- Not published