Where is Hayford Farm - extension up to?
Each status below comes from a named source and date.
Solar PV · England, West Midlands
Planning
- Planning
- Granted
- 26 Aug 2014
- DESNZ REPD, 3 Aug 2026
- Construction
- Built
- 1 Feb 2015
- DESNZ REPD, 3 Aug 2026
- Operational status
- Operational
- 26 Mar 2015
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Solar PV project, epj_9a400c4c413c0098
Measures
- Rated power
- 8.2 MW
- Connection capacity
- Not published
- Storage energy
- Not published