Where is Point Wind / Beinn Ghrideag Farm up to?
Each status below comes from a named source and date.
Onshore wind · Scotland
Planning
- Planning
- Granted
- 26 Apr 2012
- DESNZ REPD, 3 Aug 2026
- Construction
- Built
- 21 Jul 2014
- DESNZ REPD, 3 Aug 2026
- Operational status
- Operational
- 17 Jul 2015
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Onshore wind project, epj_9de2c7c22f912eb6
Measures
- Rated power
- 9.0 MW
- Connection capacity
- Not published
- Storage energy
- Not published