Where is Wick Farm (Burnham on Crouch) up to?

Each status below comes from a named source and date.

Solar PV · England, Eastern

Planning

Planning
Granted
26 Jan 2015
DESNZ REPD, 3 Aug 2026
Construction
Built
11 Sep 2015
DESNZ REPD, 3 Aug 2026
Operational status
Operational
17 Dec 2015
DESNZ REPD, 3 Aug 2026

Connection

Connection
Solar PV project, epj_9eeadd94f314c43b

Measures

Rated power
5.0 MW
Connection capacity
Not published
Storage energy
Not published