Projects
Where is Lawns Solar Farm up to?
Each status below comes from a named source and date.
Solar PV · England, North West
Planning
- Planning
- Granted
- 1 Feb 2023
- DESNZ REPD, 3 Aug 2026
- Construction
- Not started
- DESNZ REPD, 3 Aug 2026
- Operational status
- Proposed
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Solar PV project, epj_a1ca7ac19f2c3ea9
Measures
- Rated power
- 25.0 MW
- Connection capacity
- Not published
- Storage energy
- Not published